The upper anchors for the first partial stretch of the sheet pile wall have now been installed. Following filling in behind the sheet piling, part of the future quay can now be used to unload sand and rock from the dredging. 

43 Pic2jpg

The anchor beam is almost finished. A small piece is missing at each end and concrete for this will be poured next year. In the area in the picture above, anchor blocks will be set out and connected to the anchor beam with the anchor bars.  

43 Pic3jpg

With work suspended on the anchor beam, work on pouring the foundation for the workshop is now taking place. At the same time, the final foundations for the warehouse and refrigeration stores are being laid. 